Our company intends to build a 5th generation greenhouse complex in the Dnipropetrovsk region (there is no such complex in Ukraine yet) for growing vegetables.
Project summary
The resulting project indicators
Index | Result | Unit. |
|
The total cost of the project | € 13 317 007 | EUR |
|
Capital investment | € 12 697 007 | EUR |
|
Funds to start operating activities | € 620,000 | EUR |
|
Project financing conditions | |||
Loan amount | € 10 649 577 | EUR |
|
Own funds | € 2 667 431 | EUR |
|
Loan to equity ratio | 80%: 20% |
|
|
Loan terms | 6.00 | years |
|
Annual interest rate | % |
| |
Grace period | 9.00 | month |
|
Key project performance indicators | |||
Financial result at the end of the period (10th year) | € 18 333 274 | EUR |
|
Net Present Value NPV | € 4 373 852 | EUR |
|
Internal rate of return IRR | 19% | % |
|
Simple payback period PBP | 5.08 | years |
|
Discounted payback period DPBP | 6.83 | years |
|